Muritai School Board of Trustees
Newsletter – June 2012Board Report - Earthquake Readiness Survey
Tena koutou te whānau o te kura Muritai
We mentioned in our May newsletter that the
Board had independently commissioned, and received, an initial survey which
recommended a detailed assessment be undertaken of the two storey block. We had hoped that due to the strengthening
works undertaken by the Ministry of Education in 1998-2000, significant
additional works would not be required.
Last week the Board received the second,
more detailed, survey which reports on the building’s level of compliance with
the current National Building Standard (NBS).
Unfortunately the building has been assessed as being significantly
short of the current NBS and is categorised as “earthquake prone”.
The Board’s property committee immediately
met with experts from both the Ministry of Education and the engineers who
prepared the report to discuss the findings, appropriate procedures and
required remedial works. We were
encouraged by the Ministry’s proactive approach and we are both committed to
moving as quickly as possible to bring the property up to as near as
practicable to 100% of the NBS.
Importantly, we were also advised that
there are other factors in addition to the NBS calculations, which go to make
up actual risk and which also need to be considered in determining our next
steps. Central to these are the
predicted consequences of a significant earthquake which should take into
account that the calculations are based on a 1 in 1000-year earthquake and the
building use (i.e. between 8:30am and 5pm, 5 days a week vs. (say) a
residential building).
In ascertaining the impact of a significant
earthquake, we have been advised that the most important factor is the
structural characteristic of the building. Once a building is categorised
as earthquake prone (under 33% of NBS) this is then the key in determining
whether it is suitable for continued use.
There have been commercial buildings and schools in the region which
have been immediately evacuated following a structural survey and our experts,
who have been involved in some of that decision making, have advised us that
the main reason for this is that those buildings had “critical structural
weaknesses” which would result in a total or partial collapse of the building
in the event of a serious earthquake. Brick and masonry buildings are
particularly vulnerable in this regard.
The expert advice we have received is very
clear that our two-story building is of a very different construction and there
are “no notable critical structural weaknesses that need to be addressed”. Accordingly the Ministry’s recommendation, on
the advice of the engineer is that it is suitable for continued occupancy
pending remedial work. The report outlines this as follows:-
“The building in the east/west direction upstairs and
in both directions downstairs has around 1/3 of the current standard strength,
and therefore very close to a level that would not be considered earthquake
prone.
The building is primarily a timber framed two-story
building that has two concrete enclosures that support concrete stairs. Being a
timber building it will have more ductility and it is likely that the actual
capacity would be greater than those calculated. The main reason for this would
be the ability of the timber frame to displace and hold together (unlike a
brick building that would collapse suddenly once it meets its capacity),
therefore dissipating the earthquake energy. Other factors that assist are the
inherent strengths of the window frames, soft-board linings etc. that do not
have published capacities but would add to the strength of the system.
Capacities for these elements could be confirmed through detailed analysis or
laboratory testing, both of which would not be deemed economically viable for
this exercise.
As the building is timber framed we would expect that
any collapse would be partial only and as the materials are of a lightweight,
any collapse has a much reduced risk of serious injury than that of a collapse
in a heavier concrete or brick building. There are no notable critical
structural weaknesses that need to be addressed. This building is constructed from lightweight
materials and the risk of serious injury in this type of building is
significantly reduced when compared to a heavier building with a similar
calculated strength.”
Notwithstanding these mitigating factors,
as the detailed structural survey put the main block at 12% of NBS the Board
has decided that immediate remedial works should be undertaken. This has been fast-tracked and work will be
carried out next week, during the school holidays. The proposed works, as designed by the
engineers, will lift the building above 33% NBS and mean the building will no
longer be classed as “earthquake prone”.
Once a building reaches this level, we are
advised remedial works are usually scheduled over a 10-year period. The Board has determined however to be more
proactive and, in conjunction with the Ministry of Education, has this week
instructed the engineers to prepare a remedial structural design plan for the
strengthening of the remaining areas to lift the capacity of the building to,
or as near as practicable to, 100% of the current standards. The intention is to have this phase two work
completed over the Christmas holidays this year. Given the design and consent
process, the need for structural steelwork and the impact on classrooms the
Board believes this is a realistic and achievable timeframe. Having considered the alternatives and taken
expert advice the Board is confident this is the best way forward and once
completed we are told we will have one of the safest buildings in Wellington.
Obviously we are disappointed that the work
is necessary at all, particularly given the strengthening work carried out 12
years ago, however we believe it is important to move quickly and
comprehensively to ensure our families are in the safest possible
environment. We will of course report
back to the community as soon as the remedial design plan is completed to
update you on the next steps.
If you have any comments or queries or
would like to discuss anything further please do not hesitate to contact any of
the Board members. Our contact details
are as follows:-
Stuart Stock stu.stock@mac.com Chairperson
Andrew Bird bird@muritai.school.nz
Principal
Melissa Coton coton@muritai.school.nz Staff rep
Olivia Paterson oliviapaterson@xtra.co.nz
Craig Griffiths caltgriffiths@xtra.co.nz
Julie Parker wattersparker@yahoo.com
David Griffiths wgtngriffs@xtra.co.nz
Carolyn Patchett cpatchett@yahoo.com
Melissa Coton coton@muritai.school.nz Staff rep
Olivia Paterson oliviapaterson@xtra.co.nz
Craig Griffiths caltgriffiths@xtra.co.nz
Julie Parker wattersparker@yahoo.com
David Griffiths wgtngriffs@xtra.co.nz
Carolyn Patchett cpatchett@yahoo.com
Whether you are off to find some sun, some
snow or just some fun around Wellington this holidays we hope you have an
enjoyable holiday break and we look forward to seeing you all in term 3.
No comments:
Post a Comment